Delay condonation order, Madras High Court, Mohammed Shaffiq, J., dated 24.02.2026. Crl.M.P.(MD)No.1613 of 2026 in Crl.R.C.(MD)SR.No.3866 of 2026 under Section 5 of the Limitation Act, 1963; 97 days' delay in filing criminal revision case condoned on satisfaction with affidavit reasons; respondent's counsel (Ayyanar Premkumar) raised no objection; petitioner's counsel K.Palmurugan. Underlying impugned order dated 17.07.2025 in Crl.M.P.No.664 of 2023 in M.C.No.11 of 2015 by Additional Chief Judicial Magistrate Court, Madurai. Registry directed to number the revision if otherwise in order. No precedent cases cited; no monetary quantum involved.
What did the court decide?
Condonation of the delay of 97 days in filing the criminal revision case (Crl.R.C.(MD)SR.No.3866 of 2026), and direction to the Registry to number the revision case if otherwise in order; the respondent's counsel had stated no objection to allowing the petition.