Keywords: Section 138 Negotiable Instruments Act; complaint by company through authorised officer; Board Resolution authorisation to prosecute; limitation 45 days from notice service; statutory notice Ex.P5 served 01.01.2000; complaint filed 17.02.2000 time-barred; appeal against acquittal under Section 378(4) Cr.P.C.; Chandrappa vs. State of Karnataka (2007) 4 SCC 415; powers of appellate court against acquittal; TIIC loan and dishonoured cheque Rs.15,64,376/-; One Time Settlement Rs.40 lakhs rejected; mediation failed; Madras High Court CRL A No.277 of 2010; M.Nirmal Kumar, J.; acquittal confirmed; appeal dismissed.
What did the court decide?
None; the acquittal of the respondents rendered by the Judicial Magistrate No.I, Dharmapuri in C.C.No.327 of 2000 dated 09.12.2009 is confirmed. ¶123