Condonation of delay; deficit court fee; Rs.7,103/-; 579 days delay; affidavit of reasons; CMP No.4645 of 2026; Arb.Appeal Sr.No.214189 of 2025; petition ordered; Madras High Court (per mhc.tn.gov.in source); decided 20.02.2026; order by C.V.Karthikeyan, J. with K.Kumares h Babu, J. Short administrative order — no statutory provisions, no cited precedents, no quantum of award beyond the court-fee figure.
What did the court decide?
Delay of 579 days in paying the deficit court fee of Rs.7,103/- condoned; the petition was ordered. ¶8