Union of India v. C.Ramaiah(Died)
Case brief
What is this about?
Section 37 Arbitration and Conciliation Act 1996 appeal; scope of judicial review narrower than Section 34; no re-appreciation of evidence; Arbitrator master of evidence; patent illegality and public policy as sole interference grounds; Union of India MES Chief Engineer (AF) vs contractor's legal heirs (C.Ramaiah, R.Malarvalli, R.Kavibharathi, R.Venkatesh); hangar construction contract CE(AF)/BAN/31 of 2008-2009 at Sulur, Coimbatore; prolongation and loss-of-profit claim Rs.5,60,33,775/-; total award Rs.6,56,94,103/-; contract value Rs.9,66,42,000/-; Condition 11(c) no-compensation clause contention; Condition 50 of IAFW.2249 compensation notice; approved supplier Vardhman poor performance causing delay; substitution of Metal Scope (India) Private Limited; recovery of Rs.70,00,000/- towards Andaman contract; Section 34 confirmation by Principal District Judge, Coimbatore; award dated 14.03.2018; order dated 19.02.2021; C.M.A.No.1801 of 2021; C.M.P.No.9779 of 2021.