M/s.Sivashankar and Co., Rep.by its Proprietor D.Sivashankar, v. The Divisionala Railway Manager
Case brief
What is this about?
Section 34 challenge to arbitral award; termination of railway contract after expiry by efflux of time; termination presupposes subsisting contract; GCC Clause 17A(ii) extension of time; GCC 62(1) termination; Clause 16(4)(f) forfeiture of EMD PG SD; perverse finding; patent illegality; stock at site claim; loss of profit at 10% of balance work rejected; interest 9% p.a. on refunded EMD PG SD; counter claims forfeiture set aside; Southern Railway Chennai Egmore foot over bridge; Union of India v Quick Communication Systems relied on; Chief Engineer CN/East v Kalyani 2018 SCC Online Mad 2138 referred; Air India v Gati distinguished.
What did the court decide?
Arbitration Original Petition allowed: Claim Nos.1 to 4 and 7 awarded in favour of the petitioner/claimant; EMD, PG and SD to be refunded with interest at 9% p.a. from 30.06.2020 till actual payment; Rs.4,50,000 under Claim No.7 payable with interest at 9% p.a. from 30.06.2020 till actual payment; Counter Claim Nos.1 and 2 awarded by the Tribunal set aside; award confirmed in all other respects; respondent to pay costs of Rs.2,00,000 to the petitioner.