M.Subramaniam v. The Repatriates Cooperative Finance and
Case brief
What is this about?
Condonation of delay; 14 days delay; Section 34 Arbitration and Conciliation Act 1996 challenge to arbitral award; REPCO Bank; M.Subramaniam; S.Nirmala; M.S.Shyam Sundar; sufficient cause shown; Registry directed to number petition; Madras High Court; Senthilkumar Ramamoorthy; A. No. 777 of 2026; Arb.O.P.(Comm.Div.) No.SR.211401 of 2025; dated 17-03-2026.
What did the court decide?
Condonation of the 14-day delay in filing the Section 34 petition, and direction to the Registry to number the petition if otherwise in order. ¶¶31-¶33