Interest on interest; arbitral award interest at 11% per annum up to date of actual payment; award may carry interest at rate specified by arbitral tribunal; closure of execution petition refused; judgment on interest calculation memo (9% per annum from 13.05.2010 to 31.03.2016); Order XIV Rule 12 and Order XIV Rule 8 Madras High Court Original Side Rules read with Section 151 CPC; A.Nos.6473 & 6474 of 2024; A.No.6787 of 2023; E.P.No.26 of 2021; Original Petition No.654 of 2016; Union of India judgment debtor; Saravana Constructions decree holder; eight weeks' time to discharge award liability; applications dismissed without costs.
What did the court decide?
Both applications dismissed without any order as to costs; the applicant's request for eight weeks' time to discharge the liability as per the award was accepted. ¶26