A.M.Sathiyamoorthy v. The Repatriates Cooperative Finance and Development Bank Ltd.
Case brief
What is this about?
Condonation of delay; 92 days; representation of Arbitration Original Petition; Arb.O.P.DR.No.195385 of 2025; A.No.9 of 2026; affidavit of reasons; Registry directed to number petition; Madras High Court; N.ANAND VENKATESH; decided 07.01.2026.
What did the court decide?
Condonation of 92 days' delay in representing the Arbitration Original Petition; Registry directed to number the Arbitration Original Petition, if it is otherwise in order. ¶5