Murugan v. The District Collector
Case brief
What is this about?
Writ of Mandamus; Article 226 of the Constitution of India; patta cancellation; Gramathana Sarvothaiya Kotturavu Society; representation dated 21.05.2024; Survey Nos.54/1, 54/4, 54/5, 58/2A, 58/2B, 58/2D, 58/3B; Rengappanaickanpatti Village; Nilakkottai Taluk; Dindigul District; Revenue Divisional Officer directed to conduct due enquiry; opportunity to petitioner and Society; eight-week timeline; disposed of without going into merits; Madurai Bench of Madras High Court; P.B. Balaji, J.; no costs.
What did the court decide?
Third respondent (Revenue Divisional Officer, Nilakkottai Taluk) directed to conduct due enquiry and pass final orders on the petitioner's representation dated 21.05.2024, after affording opportunity to the petitioner and the Society, within eight weeks from receipt of a copy of the order; writ petition disposed of with no costs.