Ramu C v. The Executive Engineer
Case brief
What is this about?
Electricity service connection transfer; TANGEDCO; representation dated 24.03.2025 not considered; S.C.No.05-351-013-198; Survey No.339/5; 188 cents; Nallukurichi Village; Vickramapandiapuram Group; Ramanathapuram District; G.Rakku; C.Ramu; statutory authority's duty to consider representation; dereliction of duty; Article 226 mandamus; direction to consider and decide within two months; Madurai Bench; W.P.(MD)No.8982 of 2025; Vivek Kumar Singh J.; disposed 02.04.2025.
What did the court decide?
Direction to the third respondent (Executive Engineer (Distribution), TANGEDCO, Paramakudi) to consider the petitioner's representation dated 24.03.2025 on its own merits and pass appropriate orders in accordance with law, after giving due opportunity to the petitioner and the fifth respondent, within two months from receipt of a copy of the order; no view expressed on merits; no order as to costs.