Bala Sarawathi v. The Divisional Engineer
Case brief
What is this about?
Keywords: W.P.(MD)No.32534 of 2025; Bala Sarawathi vs Divisional Engineer, National Highways, Madurai; Madurai Bench of Madras High Court; decision 14.11.2025; notice dated 12.09.2025; Schedule III of Highways Administration Rules, 2004; section 26(2) and 26(3) of National Highways (Land and Traffic) Act 2002; Rule 26 of The Control of National Highways (Land and Traffic) Act, 2002; re-survey; opportunity of hearing; twelve weeks to pass orders; disposed; no costs; Andipatti Town Panchayat; Theni district; Article 226; certiorarified mandamus; followed WP(MD)Nos.27545-27550 of 2025 (order dated 03.10.2025).
What did the court decide?
Writ petition disposed: proceedings to continue afresh with hearing to the petitioner, and the authorities directed to pass orders in all similar matters within twelve weeks; no costs; connected miscellaneous petitions closed.