Mjd Construction and Engineering Contractors (P) Ltd. v. The Chief Engineer
Case brief
What is this about?
Consolidated completion certificate quashed (first phase only); separate work completion certificates for phased NH-47 EPC works; five-year maintenance period commencement from phase-wise completion; defect liability Article 14.1(i); TWAD Board pipeline work stoppage Letter dated 10.08.2020; Divisional Engineer National Highways Nagercoil; Certiorarified Mandamus Article 226; W.P(MD)No.30300 of 2023; W.M.P(MD)No.26105 of 2023; Madurai Bench Madras High Court; L. Victoria Gowri J.; decided 09.01.2025.
What did the court decide?
Quashing of the impugned consolidated completion certificate dated 14.07.2022 limited to the first phase of work; direction to the third respondent to issue two completion certificates, one for the first phase based on the test results taken during October 2020, facilitating maintenance from 30.10.2020 for five years; no order as to costs; connected miscellaneous petition (W.M.P(MD)No.26105 of 2023) closed.