Suyambulingam v. The Junior Engineer
Case brief
What is this about?
Mandamus electricity connection shifting TNEB TANGEDCO Junior Engineer representation 20.01.2025 online application fees four weeks disposal Article 226 Tirunelveli Radhapuram/Rathapuram Taluk service connection S.C.No.07070006544 coconut tree branch disruption power supply M.Dhandapani J. W.P.(MD).No.13869 of 2025 decided 08.05.2025
What did the court decide?
Writ petition disposed of with a direction to the respondent to consider the representation dated 20.01.2025 after hearing and pass appropriate orders within four (4) weeks; petitioner to file an online application with necessary fees, to be considered within two (2) weeks of its receipt; no order as to costs. ¶25