A.Ramesh Kumar, v. the Managing Director
Case brief
What is this about?
Tamil Nadu Housing Board rent arrears demand; certificate of vacation / clearance of housing board quarters, Tirunelveli; impugned Letter No.R-3/D-1/2019 dated 05.04.2019 demanding Rs.1,95,215/- plus water charges Rs.2,020/-; reworked dues of Rs.39,085.71/- per working sheet communicated on 23.12.2024; deductions by Drawing Officer; remittance from employer disputed; writ disposed with liberty to file fresh writ petition; Article 226 certiorarified mandamus; Madras High Court, Madurai Bench; Justice K. Rajasekar; W.M.P.(MD).Nos.9751 of 2019 and 19252 of 2022 closed.
What did the court decide?
Writ petition disposed of directing the petitioner to verify the reworked working sheet and, if proper, pay the amount shown therein (Rs.39,085.71/-), with liberty to file a fresh writ petition if he disputes the remittance from his employer; no order as to costs; connected miscellaneous petitions closed. The impugned demand order was not quashed and no certificate of vacation was directed.