S.B.Bowmesh v. the Panchayat President
Case brief
What is this about?
Demolition/encroachment-removal notice by village Panchayat under Section 131(2) Tamil Nadu Panchayats Act 1994 set aside where statutory appeal under Section 10 of the Tamil Nadu Land Encroachment Act 1905 against a Section 6 order was pending before the Collector; parallel proceedings during pendency of appeal held not legally sustainable; certiorari allowed and mandamus issued directing Collector (sixth respondent) to decide 92-day condonation of delay by 12.08.2025 and interim stay under Section 10-B LE Act by 09.09.2025; coercive action made subject to outcome of those applications; concerns Survey No.76/40, Urappakkam Village, Vandalur Taluk, Chengalpattu; prior writ W.P. No.4025 of 2025 (dismissed 10.02.2025) had relegated petitioner to statutory appeal.
What did the court decide?
Certiorari limb allowed: the impugned notice dated 07.07.2025 issued by the first respondent is set aside. On the mandamus limb, the sixth respondent (Collector) is directed to consider the condonation of delay of 92 days in filing the appeal dated 12.06.2025 and pass orders on or before 12.08.2025; if the delay is condoned, to consider and dispose of the interim-stay request regarding the order dated 03.01.2025 on or before 09.09.2025. Any coercive action is subject to the outcome of the condonation and interim-stay applications under Section 10-B of the LE Act. Connected Writ Miscellaneous Petition (W.M.P. No.28972 of 2025) closed; no order as to costs.