E.Raamadasan v. the Principal Secretary
Case brief
What is this about?
Unauthorised construction on government land; demolition of illegal buildings; recovery of public property land; writ of mandamus under Article 226; Greater Chennai Corporation Zone-1 Part-3 Ward-12; Srinivasa Puram 2nd street, Kaladipet, Thiruvottiyur, Chennai; Uchi Pidari Amman Kovil; HR & CE Department enquiry direction; four-month enquiry timeline; opportunity of hearing to persons alleged against; representations dated 5.12.2024, 3.1.2025, 8.2.2025; respondents 9 and 10 impleaded via W.M.P.No.34010 of 2025; disposed with directions, no costs; Madras High Court, Chief Justice Manindra Mohan Shrivastava and G. Arul Murugan J., 01.09.2025.
What did the court decide?
Writ petition disposed of with a direction to respondent No.9 (Commissioner of HR & CE) to examine the petitioner's complaint by holding appropriate enquiry, after giving opportunity of hearing to those against whom allegations are made, concluding within four months, thereafter passing appropriate order as required under law; no order as to costs.