M/S.Abirami Engineering Construction and Co. v. the Engineer-in Chief and Chief Engineer (General)
Case brief
What is this about?
Price escalation / price variation clause; base index quarter of last date of bid submission; wholesale price index; delayed execution of agreement; Tender Award Committee acceptance 06.08.2021; clause 64 payment within 14 days of certificates; clause 65.1 no-interest clause; interest on delayed payment to government contractor; commercial rate interest 10% p.a. from 15.03.2023; admitted amount Rs.1,79,92,131/-; work value Rs.55,65,00,000/-; work completed 27.02.2023; Tamil Nadu Public Works Department; New Government Dental College and Hospital Pudukkottai; Article 226 writ; contractual dispute relegated to separate suits; Madras High Court; Neutral Citation 2025:MHC:2979.
What did the court decide?
Writ petition disposed of with directions: respondents to pay the admitted amount of Rs.1,79,92,131/- with interest @ 10% p.a. from 15.03.2023 till date of payment, within four weeks; residual dispute on the base date for price variation and alleged petitioner default left to be adjudicated in separate suits; no costs; connected miscellaneous petition closed.