M/S.Ramaniyam Real ESTATES9P) Ltd, v. the Secretary to Government
Case brief
What is this about?
De-occupation notice CMDA Letter No. ES2/6126/2008 dated 18.04.2024 quash refused; unauthorized construction deviation Ramaniyam Samarpann Thiruvanmiyur; 79 vs 77 dwelling units; two extra fourth-floor flats; stilt parking converted to storage/association rooms; regularisation refused for want of consent of all flat owners and registered GPA; revised planning permission CMDA/PP/NHRB/S/0644/2023 dated 19.01.2024 not processed; SBC No.CMDA/PP/NHRB/S/0322/2024 dated 08.05.2024; earlier orders WP 11421/2014, WP 25379/2022, WP 8809 & 8813/2010; balance I & A charges Rs.44,77,000/-; Completion Certificate; enforcement direction demolition restoration within 8 weeks; writ petition dismissed no costs; Chennai Metropolitan Development Authority; Housing and Urban Development Department; impleadment WMP.9478/2025.
What did the court decide?
No relief to petitioners; Writ Petition dismissed with no costs and connected Miscellaneous Petitions closed; CMDA directed to continue enforcement, demolish unauthorized construction and restore the building per the approved plan within 8 weeks.