The Management v. T.Pachaiappan
Industrial Disputes Act, 1947 – Section 33(2)(b) – approval of dismissal – requirement of simultaneous filing
Case brief
What is this about?
Madras High Court (Single Judge, M. Dhandapani, J.), decision dated 28.03.2025, W.P.No.17107 of 2019: Certiorari petition by Tamil Nadu State Transport Corporation (Salem) Ltd. against refusal of approval under Section 33(2)(b) Industrial Disputes Act for dismissal of a Reserve driver involved in a fatal accident; approval petition filed 08.08.2012 with five days' delay and no explanation; held that unexplained delay — even a single day — is fatal to the approval petition; Lalla Ram v. D.C.M. Chemical Works Ltd. (AIR 1978 SC 1004) ingredients applied; Division Bench ruling in C.Iyandhurai (W.A. No.1555 of 2022, dt. 01.08.2022) relied on; writ petition dismissed with no costs and connected WMPs closed.
What did the court decide?
In the consistent view of the courts, there should be proper explanation for any delay in filing an approval petition, and in the absence of such explanation even a single day's delay is fatal; even where delay is claimed to be reasonable, the reasonableness must be explained.