The Superintending Engineer v. Mjd Construction and Engineering Contractors (P) Ltd.
Case brief
What is this about?
A writ miscellaneous petition sought a six-month extension for State highway officials to settle the final bill amount due to a contractor as ordered in an earlier writ petition. The court granted a four-month extension and ruled that no further extension would be given.
What did the court decide?
Four-month extension granted to comply with the earlier order; no further extension to be granted.