Gail (India) Limited v. Hindustan Oil Exploration Company Limited
Section 9, Arbitration and Conciliation Act 1996 – interim injunction
Case brief
What is this about?
Madras High Court, P.B. Balaji J., 17.02.2025 — O.A.No.968 of 2024, Arb. Application No.884 of 2024, Application No.407 of 2025 — GAIL (India) Ltd v. Hindustan Oil Exploration Co. Ltd and PPN Power Generating Co. Pvt. Ltd — Section 9 interim injunction, Arbitration and Conciliation Act 1996 — gas supply contract, PY-1 gas field, Kaveri basin, 75 sq.km contract area, existing gas discovery, three wells, clause 7.3 substitute gas option, build-up period, plateau period, DCQ 51000 to 17000 MMBTU, amendment dated 10.07.2013, force majeure invocation, implied acceptance, non-renewal beyond 17.09.2024, extinction of right to gas, privity of contract, non-signatory third party rights, disclosed end buyer, incorporation of contract/arbitration clause by reference, premature document production, no adverse inference at Section 9 stage, vacation of ex-parte injunction, M.R. Engineers (2009) 7 SCC 696, Zonal General Manager IRCON (2015) 13 SCC 680, MAC Associates 2024 SCC OnLine Del 1313, Halliburton Offshore 2020 SCC OnLine Del 2068.