Condonation of delay — 127 days and 128 days delay in representing papers; CMP Nos.28184 & 28190 of 2025 in CRP SR Nos.180370 & 180395 of 2025; Madras High Court; P.B. Balaji, J.; orders dated 13.11.2025; petitions allowed on satisfaction with affidavit reasons; Registry to number CRPs and list on 18.11.2025 under caption “For admission”; no statutes or case-law cited; suitable only as procedural precedent on condonation practice.
What did the court decide?
Both CMPs allowed: the delay of 127 days (CRP Sr.No.180370 of 2025) and the delay of 128 days (CRP Sr.No.180395 of 2025) in representing the papers stand condoned; Registry directed to number the Civil Revision Petitions and list them on 18.11.2025 under the caption “For admission”. ¶9