P.Ganesan v. R.Ranjani
Case brief
What is this about?
Madras High Court, C.M.P. No. 20171 of 2022 in Cros.Obj.SR.No.27847 of 2020, Dr. A.D. Maria Clete, J., decided 08.09.2025: condoned a 153-day delay in representing a cross objection, accepting the affidavit explanation that counsel's viral infection caused the delay in rectifying defects, holding the delay neither wilful nor wanton, and directing the Registry to number the cross objection if otherwise in order.
What did the court decide?
Delay of 153 days in representing the cross objection condoned; Registry directed to number the cross objection if it is otherwise in order. ¶6