M/s.N.Shajahan Engineering Works v. M/s.Akshobhaya Steels Private Limited
Case brief
What is this about?
Condonation of delay; 89 days' delay; re-presentation of Arbitration Original Petition (Commercial Division); Arb.O.P.(Com.Div.) D.No.189954 of 2025; A.No.6272 of 2025; Madras High Court; single judge; N. Anand Venkatesh, J.; application allowed; order dated 16.12.2025.
What did the court decide?
Condonation of the delay of 89 days in re-presenting Arb.O.P.(Com.Div.) D.No.189954 of 2025. ¶3