The Union of India v. Rpn Engineers Chennai Pvt. Ltd.
Case brief
What is this about?
Condonation of delay; Section 34 Arbitration and Conciliation Act 1996; challenge to arbitral award dated 16.05.2025 and rectification order dated 20.06.2025; Arb.F.No.05 of 2022; Union of India / Southern Railway v. RPN Engineers Chennai Pvt. Ltd.; Madras High Court Commercial Division arbitration side; 20-day delay condoned; petition allowed and directed to be numbered and posted for admission.
What did the court decide?
Condonation of the 20-day delay in filing the Arbitration Original Petition under Section 34 of the Arbitration and Conciliation Act, 1996; Registry directed to number the petition and post it for admission; petitioner's counsel directed to serve all papers on respondent's counsel, whose name is to be printed in the cause list at the time of admission. ¶26