Numaligarh Refinery Limited, v. M/s. Solar Design Pvt. Ltd.
Case brief
What is this about?
Condonation of delay; 12 days delay in re-presentation/refiling of Arb OP (Comm Div) D No.119628 of 2025; delay only in refiling not in filing; petitioner company situated at Assam; lenient view; followed OSA.No. 66 of 2023 (Division Bench; 267 days delay condoned; Rs.25,000/- costs deleted; judgment dated 29.03.2023) and A.No. 1219 of 2023 in Arb.OP.DR.No. 9142 of 2022 (Single Judge; allowed without cost); Application No. 1232 of 2023 dated 03.03.2023 referred; Madras High Court Master order dated 26.08.2025; no order as to costs.
What did the court decide?
Delay of 12 days in representing Arb OP (Comm Div) D No.119628 of 2025 condoned; application allowed with no order as to costs. ¶14