Mr.H.Sunil Kumar v. Mr.M. Deepak Kumar Samdariya
Arbitration and Conciliation Act, 1996 – S.34 – Petition to set aside arbitral award
Case brief
What is this about?
Order dated 04.08.2025 (Master) in A.Nos. 3697 of 2025 in Arb.OP.D.No.95620 of 2025 condoning a 1-day delay in re-presenting an original petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award, where the delay was caused by technical glitches in the e-filing portal; leniency extended following OSA.No. 66 of 2023 (Division Bench) and A.No. 1219 of 2023 in Arb.OP.DR.No. 9142 of 2022 (Single Judge); application allowed without costs (court identified from mhc.tn.gov.in).
What did the court decide?
Condonation of the 1-day delay in representing the original petition under Section 34 of the Arbitration and Conciliation Act, 1996; application allowed with no order as to costs. ¶17