Sas Hydel Projects Private Limited, Represented by its Whole Time Director v. B Fouress Private Limited
Case brief
What is this about?
Arbitration — extension of mandate of Arbitral Tribunal by four months — trial concluded, applicant's arguments advanced, final award pending — respondent raised no serious objection — Madras High Court, single Judge (P.B. Balaji, J.) — A. No. 244 of 2025 — SAS Hydel Projects Private Limited v. B Fouress Private Limited — order dated 23.01.2025.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal by four months from 23.01.2025. ¶21-22