M/s. Engineering Projects (India) Limited v. Tamil Nadu Housing Board
Case brief
What is this about?
Madras High Court; A No. 1579 of 2025 in EP No. 67 of 2024; order dated 10-11-2025; Justice N. Anand Venkatesh; M/s. Engineering Projects (India) Limited (applicant/petitioner, authorised signatory Barun Kumar Saha); Tamil Nadu Housing Board (respondent/judgment debtor); Axis Bank Ltd (garnishee); execution petition closed; application for affidavit of assets closed; interim stay of implementation of arbitral award in operation; interim order in A.No.3351 of 2025 dated 21.07.2025 complied with; main Arb.O.P.No.402 of 2025 to be heard on 20.11.2025.
What did the court decide?
Because the interim order in A.No.3351 of 2025 dated 21.07.2025 has been complied with and an interim stay in the implementation of the arbitral award is in operation, it will be more appropriate to take up the main original petition; accordingly, both the application (A No. 1579 of 2025) and the execution petition (EP No. 67 of 2024) shall stand closed.