M.Ramakrishnan v. The Secretary to Government
Case brief
What is this about?
This writ petition concerned the petitioner's unpaid bill for contractual works executed for the Water Resource Department. The Madurai Bench of Madras High Court directed the first respondent to settle the bill amount within three months. Failure to comply within this period attracts interest at 6% per annum.
What did the court decide?
The first respondent directed to settle the bill amount within three months. Interest at 6% per annum payable if payment is delayed beyond the stipulated time.