and the petitioner was directed to pay Rs.8,15,030/-, however, since the petitioner has requested the first respondent to consider the fresh, application dated 13.01.2020 and not insisted on the earlier applications, which were filed under wrong category, the petitioner was under the belief that the earlier applications would not be considered, in such state of confusion, the petitioner failed to comply with Form-3 dated 22.01.2020, resulting in the Portals getting closed, hence, the petitioner made representations dated 02.03.2020 & 22.06.2020, to the first respondent, thereby, requesting them to re-activate the Scheme Portal so as to enable the petitioner to make the payment as per Form-3 dated 22.01.2020 issued by them. However, as on date, the said representations have not been considered, which necessitated the petitioner to approach this Court by way of the present Writ Petition. The learned counsel for the petitioner also placed reliance on a decision rendered by the Hon'ble Division Bench of this Court in the case of Win Power Engineering (P) Ltd., Vs. The Designated Committee, Sabka Vishwas Legal Disputes Resolution Scheme, in W.P.Nos.11785, etc.