M/s.Ece Industries v. The Chairman
Case brief
What is this about?
A transformer supplier sought payment for erected and commissioned transformers and release of bank guarantees from TANGEDCO. Holding liability was admitted and no disputed facts arose, the court held the writ maintainable and directed payment of the balance amounts within four weeks.
What did the court decide?
Respondents to pay Rs.1,63,21,901/- within four weeks and Rs.60,34,176/- after invoice bill furnished; writ disposed with no costs.