J.Balaji v. State Government of Tamilnadu
Case brief
What is this about?
The High Court directed the respondents to pay outstanding amounts of Rs.19,52,930 and Rs.13,20,932 owed to two contractors for completed repairs at GCAS, Mamallapuram, within eight weeks, with interest liability on delay.
What did the court decide?
Respondents directed to pay Rs.19,52,930 and Rs.13,20,932 within 8 weeks; Respondent No.2 liable to pay interest on delay.