R.Krishnamurthy v. the District Collector
Case brief
What is this about?
Petitioner sought removal and realignment of High Tension towers and wires erected through his land despite his objection, offering to bear shifting costs. The Board's counsel undertook that the representation would be considered by the Chief Engineer, Transmission Project, TANTRANSCO. The Court directed consideration of the representation and final orders within six weeks.
What did the court decide?
Direction to Chief Engineer, Transmission Project, TANTRANSCO, Guindy to consider petitioner's representation dated 14.09.2024 and pass final orders within six weeks.