Accudyne Industries India Private Limited v. M/S. R.P. Rajarajan Enterprises
Case brief
What is this about?
The High Court disposed of two appeals regarding a built-to-suit lease dispute. It held the lessor's termination of the lease invalid as delays were caused by the lessee. The court awarded the lessee no refund but denied the lessor's claim for base rent, holding the advance amount retained as compensation for construction work to avoid unjust enrichment.
What did the court decide?
The lease termination was upheld as illegal; base rent award set aside; advance money retained as compensation; counter-claim for refund dismissed.