Banupriya v. R. Govindaraj
Case brief
What is this about?
The tenant vacated the premises while a rent control appeal was pending. The High Court directed the lower court to dispose of the pending appeal within two months and disposed of the Civil Revision Petition.
What did the court decide?
Disposed of the petition with a direction to dispose of the pending appeal within two months.
What the court decided
C.R.P. (NPD) No.2713 of 2024
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED :26.07.2024
CORAM :
THE HON'BLE MR.JUSTICE M.NIRMAL KUMAR
Civil Revision Petition (NPD) No. 2713 of 2024
Banupriya
.. Petitioner
Versus
R.Govindaraj .. Respondent
Prayer : Civil Revision Petition filed under Section 151 of CPC, to set aside the impugned Judgment and Decree dated 05.03.2024 in E.P.No.247 of 2023 in R.C.O.P.No.128 of 2016 on the file of the learned Rent Controller cum Additional District Munsif, Coimbatore.
For the Petitioner : Mr.P.Madhavan
Issues for consideration
1 issue framed by the court
Whether the Civil Revision Petition regarding execution of eviction decree should be disposed of given the premises were vacated and the appeal is pending?
Parties & counsel
- petitioner
Banupriya
- respondent
R.Govindaraj
Coram
M.NIRMAL KUMAR
Case details
As recorded by the court registry
Similar cases