United India Insurance Co.Ltd v. Opg Power Generation Private Limited
Case brief
What is this about?
Application to condone an 88-day delay in filing the written statement in a fire-claim commercial suit, citing administrative reasons and need to obtain particulars. No objection from plaintiff; court allowed with Rs.2,500 costs.
What did the court decide?
Delay of 88 days in filing written statement condoned subject to payment of Rs.2,500/- costs to respondent's junior counsel by 10.04.2024.