Sai Pranav Wind Power Private Limited v. Rajesh Lakhoni
Case brief
What is this about?
This is a single bench order closing a contempt petition filed under Section 11 of the Contempt of Courts Act against TANGEDCO officials. The court noted that the impugned orders were complied with and arrears were paid, thereby closing the petition and a connected sub-application.
What did the court decide?
Contempt petition and connected sub-application closed.
What the court decided
Cont.P.No.681 of 2023
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 11.04.2023
CORAM :
The HONOURABLE DR.JUSTICE ANITA SUMANTH
Cont.P.No.681 of 2023 and
Sub.Appl No.203 of 2023
Sri Saipranav Wind Power Private Limited Rep. by its Managing Director Mr.P.S.Mylsamy, 41, Majid Street, Kangayam - 638 701 Tirupur District.
.. Petitioner
vs
1.Rajesh Lakhoni The Chairman, Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO), 144, Anna Salai, Chennai - 600 002.
2.Mrs.K.Malarvizhi
The Chief Financial Controller (General) TANGEDCO, N.P.K.R.R.Maligai, 144, Anna Salai, Chennai - 600 002.
Issues for consideration
1 issue framed by the court
Whether the allegations of contempt against respondents regarding compliance of prior orders are admitted.
Parties & counsel
- petitioner
Saipranav Wind Power Private Limited
- respondent
Rajesh Lakhoni
- respondent
Mrs. K. Malarvizhi
- respondent
A. Subramanian
- respondent
S. Ilamparithy