to construct 31 individual houses in the above property under the name and style “Priyadharsini Villas”; the respondent had executed a joint Power of Attorney on 06.06.2011 in favour of the petitioner to deal with the above property; due to some extraordinary reasons, the respondent had agreed for entering into a supplementary deed dated 10.04.2013 to the above joint venture agreement dated 20.04.2011 wherein it was agreed to extend the time limit for construction up to 20.04.2015; the construction of houses could not be completed even during the extended period due to non-cooperation by the respondent by providing the individual patta; however the respondent unilaterally cancelled the power of attorney dated 06.06.2011 and issued notice to the petitioner as though he is the reason for the delay; the respondent issued a legal reply to the petitioner and demanded a sum of Rs.1,90,69,868/- towards expenses incurred to develop the property and for putting up construction.