The Madurai Bench of the Madras High Court disposed of a writ petition filed for a direction to restore electricity connection and allow installment payment. The court directed restoration upon payment of a lump sum, with the balance payable before a specified date.
What did the court decide?
Restoration of electricity connection on payment of Rs. 13,00,000/-; balance amount payable by 09.01.2023.