E.Jothi v. the Assistant Engineer
Case brief
What is this about?
In this writ petition, the petitioner sought a mandamus directing the Assistant Engineer to process an application for electricity connection in poramboke land. The Court directed the respondent to pass final orders within eight weeks, following the precedent set in N.Senthil case, and to grant a personal hearing.
What did the court decide?
Direction to the first respondent to pass final orders on the application for electricity connection within eight weeks, affording a fair hearing including personal hearing.