M/s.Sakthi Steel Industries v. The Chairman and Managing
Case brief
What is this about?
The High Court of Madras allowed a writ petition contesting a demand for harmonic distortion charges imposed on an industrial consumer. The court held that the authority failed to issue the mandatory three-month notice required before collecting compensation. It quashed the demand and remitted the matter to the respondents to follow the proper procedure.
What did the court decide?
The impugned demand for Rs.90,39,748/- under item No.14 was quashed, and the matter was remitted to the respondents to reconsider and pass fresh orders within three months after giving a proper statut