M/S Suzlon Energy Ltd. v. G.Shashank Sai, I.P.S
Case brief
What is this about?
In a contempt petition alleging non-compliance with an order to pay 500% compensation for land acquisition, the single-judge High Court of Madras found the Petitioner company deposited the required funds. The Court directed official respondents to provide police/revenue protection for the ongoing project and ordered disbursement of compensation to landowners.
What did the court decide?
Direction to official respondents to provide police/revenue protection; order to District Collector to disburse compensation within one month; liberty to aggrieved parties to approach legally.