M/s. Thiraviam Engineering Pvt. Ltd., v. M/s. Felguera Gruas India Pvt. Ltd.
Case brief
What is this about?
The High Court granted an extension of six months for an Arbitral Tribunal to make an award. Both parties requested an extension, citing delays caused by circumstances beyond their control, specifically the COVID-19 pandemic.
What did the court decide?
Extension of time for the Arbitral Tribunal to make the award by six months, up to 28.12.2022.