Win Power Engineering Pvt. Ltd. v. Tamilnadu Generation and Distribution
Case brief
What is this about?
This single-judge bench allowed the writ petition under Article 226, directing the respondent utility to permit the switch from EPA to EWA for captive consumption and settle dues as per a common order previously issued and upheld by this Court and the Supreme Court.
What did the court decide?
Permitted migration from EPA to EWA and directed payment of dues with interest within two months.