Als Constructions, v. The Project Director
Case brief
What is this about?
The High Court refused to direct payment of a disputed price adjustment sum under a construction contract. Noting erroneous interpretation of contract clauses by the adjudicator and conflicting departmental orders, the Court directed fresh adjudication by an appointee within six months rather than settling the dispute via writ jurisdiction.
What did the court decide?
Directed respondents to appoint an Adjudicator for fresh adjudication of disputed facts within six months; Writ Petitions disposed of.