M/s.Empee Hotels Limited v. M/s.Ncc Limited
Case brief
What is this about?
A construction award was challenged over delay, liquidated damages, alleged abandonment and time being the essence of the contract. Applying the pre-amendment Section 34 regime, the Court found no demonstrated patent illegality and declined appellate reappreciation of evidence. The petition was dismissed without costs; the sole arbitrator was deleted from the parties.
What did the court decide?
The sole arbitrator was deleted from the array of respondents.