M/s.East Coast Constructions v. M/s.Sri Balaji Educational
Case brief
What is this about?
This court decreed a suit for recovery of money arising from a construction contract. It held the suit was not barred by limitation as certification occurred later. The plaintiff was entitled to the Final Bill and Retention Money but claimed VAT difference lacking evidence. The suit was partly decreed.
What did the court decide?
Defendant directed to pay Rs. 44,36,059.66 with interest at 12% p.a. and further interest at 9% from the date of decree; other reliefs dismissed.