Nos.49 and 50 of 2021 in C.P.No.298 of 2014…
A compact analysis
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
Company Application Nos.49 and 50 of 2021 in C.P.No.298 of 2014
SENTHILKUMAR RAMAMOORTHY J.
After the dismissal of the original side appeals against the order dated 08.10.2021, in Company application Nos.49 and 50 of 2021, the respondent seeks further time to comply with the said order. The order in Company application No.49 of 2021 was for the production of documents listed in the schedule thereto. On behalf of the applicant it is submitted that one of the documents listed in such schedule is the business transfer agreement between the respondent and a 3rd party dated 05.08.2011. The respondent is directed to produce the said document on or before 10.12.2021.
- List the matter on 10.12.2021 to report compliance with regard to the production of the above mentioned document.
03.12.2021
gd
1/2
gd
SENTHILKUMAR RAMAMOORTHY J,
Coram
SENTHILKUMAR RAMAMOORTHY J.
Case details
As recorded by the court registry
Similar cases
Judgements on the same questions, provisions and authorities, from every court