Regen Powertech Pvt. Ltd. v. Veeral Controls Private Ltd, Cin U33130GJ1990PTC013777
Case brief
What is this about?
of 2019 P.T.ASHA, J., Though the order dated…
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
A.Nos.578 and 579 of 2019
P.T.ASHA, J.,
Though the order dated 23.01.2019 was passed by this Court and the applicant had undertaken to initiate arbitral proceedings within a period of four weeks no arbitral proceedings have been initiated till date. There appears to be no manifest intention to arbitrate the dispute between the parties and the applicant is only keen on obtaining interim orders in violation of the provisions of Section 9(2) of the Act.
Hence, these Applications are dismissed. It is needless to state if the applicant moves the Arbitral Tribunal it is open to the applicant to file such application as advised.
29.03.2021
mps
1/1
P.T. ASHA
As recorded by the court registry